ASX Announcement
28 May 2024
Update on the Kanyika Niobium Project
Highlights
•
Capital funding requirements for Phase 1 project development have been finalised at US$46
million, inclusive of a 25% project contingency allocation.
•
The Phase 1 project development plan is confirmed with a clear path to project construction.
•
A funding strategy has been formulated to best support the Project and minimise shareholder
dilution, consisting of:
•
o
equity-related funding, including strategic equity funders contributing approximately
US$8 million;
o
project debt amounting to approximately US$15 million;
o
convertible instruments totalling approximately US$9 million; and
o
offtake pre-financing of approximately US$14 million.
Globe’s metallurgical test work on its Chlorination Refinery is progressing as planned and
previously announced.
Globe Metals & Mining Limited (ASX: GBE) (“Globe” or “Company”) is pleased to announce an update
of the Kanyika Niobium Project capital cost and funding plan.
The Company announced the completion of its Optimisation Study on 5 February 2024 1. The key
aspects of the Optimisation Study were:
1.
Pre-tax NPV (8%) of US$1.004Bn and IRR of 47.08%.
2.
The total unit cost of Niobium Pentoxide reduces by 15% to US$18.90/kg and gross profit
margin increases by 5% to 71%.
3.
27-year life of mine.
4.
Two-Phase development approach allows a significant reduction in initial upfront capital from
US$70m to US$46m and greatly reduces the risk profile of the Project.
1 Refer to ASX Announcement titled ‘Globe completes Optimisation Study at Kanyika’ made on 5 February 2024
5.
Change in refining technology to the chlorination process, which is more environmentally
sustainable, cost-effective, and produces high-purity products that can command premium
prices, and the preferred location of the Refinery in Malawi.
The Company has made significant strides in finalising its funding strategy for the Project’s first phase.
This announcement outlines the comprehensive funding plan expected to be implemented.
Updated Estimate of Project Capital Cost
The total funding required for Phase 1 first production, including working capital and indirect costs is
estimated at US$46 million.
Table 1: Kanyika Project Phase 1 capital cost estimate
Funding instrument
Capex Mine
Capex Refinery
Total Capex per Optimisation Study in Phase 1
Working Capital
Subtotal
Contingency of 25%
Subtotal
Other Indirect costs to produce first refined product
Total
Amount
US$17m
US$12m
US$29m
US$3m
US$32m
US$8m
US$40m
US$6m
US$46m
Phase 1 Funding
The Company has made significant progress in formulating the funding strategy of Phase 1, emphasising
practicality, viability, and risk mitigation within the funding package. This package is expected to consist
of equity, project debt, convertible notes, and pre-shipment financing.
The equity funding could involve a general issue of shares to the market, along with allocations to
cornerstone investors. Discussions with the cornerstone investors are well-advanced but remain
ongoing. The Company is committed to minimising the dilution of existing shareholders as much as
possible and believes the Phase 1 financing package will address this concern.
Progress on project debt and convertible note funding is also advanced, with negotiations in progress.
The Company has received substantial support from global and regional development institutions,
which will play a crucial role in providing the necessary debt and convertible note funding for the
Project.
Strategically, the Company has decided to focus on Western principal (OEM) refined products offtake
and has finalised a “target list” of strategic off-takers. Discussions regarding the long-term offtake of its
main high-purity products (Niobium, Tantalum, and Zirconium) are progressing well.
The table below displays the different financing ranges and their average amounts for the mining,
concentrator, and refinery project.
2
Funding instrument
Equity
Project and debt financing
Convertible notes
Pre-shipment offtake funding
Total
Range from
US$6m
US$10m
US$7m
US$9m
Range to
US$10m
US$20m
US$11m
US$19m
Average
US$8m
US$15m
US$9m
US$14m
US$46m
Project Execution Phase
Phase 1 development of the Kanyika Project is progressing mostly on schedule, despite minor delays
caused by the relocation of the refinery to Malawi. These delays are due to the work required for the
Environmental and Social Impact Assessment (ESIA) and the incentives associated with the Export
Development Zone, which are expected to be finalised shortly.
As announced on 20 March 2024 2, the Company has made significant advancements in the
metallurgical test work for its Chlorination Refinery, successfully completing laboratory tests and metals
extraction tests. Globe is now commissioning its laboratory-scale Chlorination Refinery, with an
announcement expected soon. The pilot-scale refinery will produce marketing samples to support
ongoing offtake agreement discussions.
Following the pilot refinery phase, the Company will update its feasibility study to include the
construction of the Chlorination Refinery in Malawi. This update will encompass the finalisation of the
ESIA and its approval by Malawian authorities.
The Company anticipates commencing the execution of its Phase 1 project by the end of 2024,
beginning with the front-end engineering and design phase, followed by project construction scheduled
for early 2025.
Paul Smith, Globe’s CEO commented: “It is fantastic to see how well our Kanyika Project has been
received by the Government of Malawi, shareholders, and funding institutions. Our Project has taken a
material leap forward in its journey into development and eventually production. I would suggest that
the Project is being materially de-risked from a funding perspective, which paves the way forward for
the Project in many respects. I must thank the Government of Malawi and our exceptional board and
management team, for bringing the Project to this exciting point in its journey into development. We
look forward to making some really exciting announcements shortly in terms of our refining pilot plant
and of course the finalisation of funding commitments, currently under discussion.”
Authorisation for Release
This announcement has been authorised for release by the Company’s Chief Executive Officer, Paul
Smith.
2 Refer to ASX Announcement titled ‘Further metallurgical results on chlorination test work’ made on 20 March
2024
3
For further information, please contact:
Paul Smith
Chief Executive Officer
+61 8 6118 7240
paul.smith@globemm.com
About the Kanyika Niobium Project
The Kanyika Niobium Project is located in central Malawi, approximately 55km northeast of the regional centre of
Kasangu and is secured by Large-Scale Mining Licence No. LML0216/21 which grants the Company security of
tenure and the right to mine niobium, tantalum, and deleterious uranium.
Drilling programs totalling 33.8 kilometres of percussion and core drilling have defined the extent of
mineralisation. Structured and progressive engineering studies have resulted in the current (JORC 2012) Mineral
Resource Estimate (refer below) and given rise to significant improvements and simplifications in the process
flowsheet.
The Kanyika operations will produce a pyrochlore mineral concentrate that contains both niobium and tantalum in
commercially valuable volumes to be shipped to a refinery for advanced processing into high purity materials.
A Mineral Resource Estimate for the Kanyika Niobium Project under the 2012 JORC guidelines was reported to
ASX on 11 July 2018 as follows:
4
Table 1: MRE for KNP using a 1,500 ppm Nb2 O5 lower cut
Category
Resource
(Mt)
Measured
5.3
Indicated
47
Nb2 O5 (ppm)
Table 2: MRE for KNP using a 3,000 ppm Nb2 O5 lower cut
Resource
(Mt)
Nb2 O5 (ppm)
Ta2 O5 (ppm)
Ta2 O5 (ppm)
Category
3,790
180
Measured
3.4
4,790
220
2,860
135
Indicated
16.6
4,120
160
Inferred
16
2,430
120
Inferred
2.8
4,110
190
TOTAL
68.3
2,830
135
TOTAL
22.8
4,220
190
Mineral Resource Estimates
The information in this report that relates to Mineral Resources is extracted from the report titled “Kanyika Niobium Project –
Updated JORC Resource Estimate” released to the Australian Securities Exchange (ASX) on 11 July 2018 and available to view
at www.globemm.com and for which Competent Persons’ consents were obtained. Each Competent Person’s consent remains
in place for subsequent releases by the Company of the same information in the same form and context, until the consent is
withdrawn or replaced by a subsequent report and accompanying consent.
The Company confirms it is not aware of any new information or data that materially affects the information included in the
original ASX announcement released on 11 July 2018 and, in the case of estimates of Mineral Resources, that all material
assumptions and technical parameters underpinning the estimates in the original ASX announcement continue to apply and
have not materially changed. The Company confirms that the form and context in which the Competent Persons’ findings are
presented have not been materially modified from the original ASX announcement.
Full details are contained in the ASX announcement released on 11 July 2018 titled ‘Kanyika Niobium Project – Updated JORC
Resource Estimate’ available to view at www.globemm.com.