ASX Announcement
28 October 2026
Quarterly Activities Report – September 2026 Quarter
During the September 2026 quarter, Globe made significant progress at its Kanyika
Niobium and Tantalum Project, completing key site development works, Phase 1
compensation payments and resolving longstanding community legal proceedings,
while advancing strategic funding and offtake discussions.
Following quarter-end, the Company commenced physical mining operations in
October 2026, marking an important development milestone towards its target of first
production in early 2028.
Highlights
• Mine Development: Completed access road upgrades, prepared mining areas
and upgraded site infrastructure at Kanyika.
• Phase 1 Compensation: Completed compensation payments to all 203 project-
affected households, enabling progression of mine development activities.
• Legal Proceedings: Resolved longstanding community legal proceedings dating
back to 2017.
• The Malawi Mining and Minerals Regulatory Authority (MMRA) Director General
provided guidance for a further six-month extension of the development
milestone, subject to MMRA Board ratification, requiring additional substantial on-
site development works that may necessitate significant additional funding.
• Commencement of Early Mining Activities (Subsequent Event): Commenced
mining activities in October 2026, with progressive excavation in batches of
approximately 5,000 tonnes to support bulk sampling, grade verification, ore
stockpiling and mine infrastructure development.
• Funding: Received A$1.59 million from option exercises and increased the
Director working capital facility to US$1.6 million.
• Strategic Partnerships: Continued progressing project funding and offtake
discussions to support Final Investment Decision.
• Cash Position: Cash at bank at 30 September 2026 was A$3.52 million (30 June
2026: A$2.78 million).
Globe Metals & Mining Limited (ASX: GBE) (Globe or Company) is pleased to
announce its Appendix 5B cashflow report for the quarter ended 30 September 2026
(Q1 FY27), together with the following operational update.
During the quarter, Globe made significant progress in advancing its Kanyika
Niobium and Tantalum Project in Malawi, completing key physical development
works, Phase 1 compensation payments and the resolution of longstanding
community legal proceedings.
The Company strengthened its financial position through A$1.59 million in option
exercise proceeds and an increased US$1.6 million working capital facility, while
continuing to advance strategic funding and offtake discussions to support the
Project's development.
Following quarter-end, Globe commenced physical mining operations in October
2026, representing an important transition towards active mine development, with the
Company continuing to target first production in early 2028.
Globe’s Interim Chief Executive Officer, Charles Altshuler, commented:
“The September quarter represented an important period of progress for Globe, with
the completion of several key milestones that have established the foundations for
the next stage of development at Kanyika.
The completion of compensation payments to all 203 Phase 1 project-affected
households, together with the resolution of historical legal proceedings dating back to
2017, represents a significant achievement for the Company and the communities
surrounding the Project.
We also made substantial progress on the ground, completing access road
improvements, preparing mining areas and upgrading site infrastructure. These
activities have enabled us to commence physical mining operations in October,
marking an important transition from preparatory works to active mine development.
Our engagement with the Malawi Government and the MMRA remains a priority as
we progress the permanent infrastructure required for the Project. In parallel, we
continue to advance discussions with potential strategic investors and offtake
partners, recognising the importance of aligning project funding, construction and
long-term commercial arrangements.
The fundamentals of Kanyika remain compelling, supported by our Bankable
Feasibility Study and the strategic importance of developing an alternative source of
niobium and tantalum supply.
Our focus remains on maintaining development momentum, progressing a
commercially sustainable funding solution and advancing Kanyika towards first
production in early 2028, while maximising long-term value for shareholders.”
Corporate and Financing Update
Exercise of options
Under the Company's A$8.67 million two-tranche placement completed in late 2025,
Globe issued 190,000,000 free-attaching options as follows:
• 152,560,000 options were issued to Avocado Trading Limited; and
• 37,440,000 options were issued to Suitable Pioneer Limited.
The options were issued on the basis of approximately 1.12 options for every
placement share subscribed, had an exercise price of A$0.069 per option, and were
due to expire one year from the date of issue. The options were non-listed but
transferable.
Subsequent to their issue, Avocado Trading Limited and Suitable Pioneer Limited
transferred all of their options to Hong Kong Green Energy Industrial Co., Ltd (Green
Energy). As Green Energy became the registered holder of the options, it acquired
the right to exercise them in accordance with their terms.
On 30 July 2026, Green Energy exercised 9,249,497 options, representing total
exercise proceeds of A$638,215. On 12 August 2026, Green Energy exercised a
further 13,854,478 options, representing total exercise proceeds of A$955,959.
Green Energy is a Hong Kong-based clean energy and infrastructure company that
provides integrated engineering, procurement, construction and energy solutions. Its
capabilities include solar photovoltaic (PV) systems, battery energy storage systems
(BESS), diesel and gas power generation, wind power generation, and hybrid
microgrid solutions. The company offers end-to-end services encompassing project
design, engineering, manufacturing, construction, logistics, commissioning, operation
and maintenance. The company is also developing and pursuing renewable energy
and infrastructure opportunities in Africa as part of its international expansion
strategy.
Working Capital Facility
As announced on 4 August 2026, Globe entered into an unsecured working capital
facility with Director Mr Bo Tan for up to US$600,000, bearing interest at 12% per
annum.
During the quarter, the Company agreed to vary the facility, increasing the total
available amount to US$1.6 million, extending the repayment date to 30 June 2027
and increasing the interest rate to 16.5% per annum. The facility remains unsecured,
with all other terms unchanged.
The increased facility provided funding to support the completion of compensation
payments to all 203 Project Affected Persons (PAPs) under Phase 1 of the Kanyika
resettlement programme, enabling the Company to advance site development
activities and progress the broader resettlement programme.
ASX: GBE
+61 8 6118 7240
info@globemm.com
globemm.com
Final Investment Decision (FID)
As previously announced, Globe targeted FID in Q3 2026. The Company continues to
progress the workstreams required to support FID, including following recent
regulatory engagement with the MMRA.
The Company is prioritising the next phase of permanent infrastructure works as part
of Kanyika's existing development programme to demonstrate readiness for
commencement of substantial mining operations and to advance the Project towards
construction and production.
In parallel, Globe continues to advance funding and offtake arrangements required to
support FID. These workstreams are closely interconnected, and Globe is conducting
a thorough evaluation to ensure that any pathway to FID reflects commercially
aligned, durable long-term development outcomes for Kanyika while preserving
financial flexibility.
The Company remains focused on its objective of achieving first production in early
2028, subject to securing the necessary funding, completing FID and achieving the
required construction and commissioning milestones.
Sinomine Transaction Update
The Company continues discussions with Sinomine regarding a potential strategic
investment in the Kanyika Project, including alternative transaction structures. The
parties remain engaged in commercial negotiations and due diligence, with a view to
reaching mutually acceptable terms. No binding agreement has been reached at this
stage.
Kanyika Niobium Project – Operational Update
During the September 2026 quarter, Globe made significant progress towards the
development of its Kanyika Niobium Project (Kanyika or Project) in Malawi,
advancing physical site development activities, resolving longstanding community
legal proceedings, completing Phase 1 compensation payments and engaging with
the MMRA on the next phase of mine development.
These activities represent important steps in transitioning Kanyika from project
preparation towards physical mine construction and ultimately commercial
production, targeted for early 2028.
Physical Mine Development and Site Preparation
On 24 August 2026, Globe announced the commencement of physical on-site
development activities at Kanyika, following completion of the Bankable Feasibility
Study (BFS) earlier in the year.
Heavy equipment was mobilised to site to undertake road grading, access
improvements, site clearing and preparation of areas required for future mining
operations and supporting infrastructure.
The works included upgrading sections of the 5.8 km of the main access road
connecting the T325 road to the mine site, together with approximately 1.4 km of
internal mine access roads, representing a combined programme of approximately
7.2 km. These improvements were undertaken to establish safe and trafficable
access for personnel, equipment and construction activities.
In parallel, Globe progressed the clearing and preparation of areas designated for the
ore stockpile and waste mining operations. The planned ore stockpile area covers
approximately 6,500 m², while the two waste mining areas cover approximately
14,000 m² and 15,800 m² respectively, providing a combined waste mining footprint
of approximately 30,000 m².
Image 1: Land clearing at the Kanyika site
These areas are intended to support initial mining activities and the extraction of
waste rock for use as construction material in Project earthworks, including platforms,
terraces and foundations.
The Company also completed improvements to the existing Kanyika exploration
camp, including accommodation for up to 12 personnel and upgrades to power,
water, ablution, shower and kitchen facilities. Additional areas were prepared for the
installation of site containers to provide office and storage facilities.
By the end of the quarter, the principal pre-development works had been completed,
establishing improved site access and operational infrastructure to support the next
stage of development.
Resolution of Historical Community Legal Proceedings
On 14 September 2026, Globe announced the formal withdrawal and discontinuance
of longstanding legal proceedings brought by members of the Kanyika community
against Globe Metals & Mining (Africa) Limited and the Attorney General of Malawi.
The proceedings, commenced in August 2017 by 243 community members, related
to historical exploration activities and associated compensation and resettlement
matters.
A Notice of Withdrawal and Discontinuance was filed in the High Court of Malawi,
formally discontinuing the proceedings and all claims against both defendants.
The resolution brought to an end a legal matter that had remained outstanding for
approximately nine years and had previously been disclosed as a contingent liability
in Globe's Annual Report.
Importantly, the withdrawal of the proceedings, together with the continued
engagement of affected communities, provided greater certainty for Globe to
progress the current compensation, resettlement and land access programme
required for mine development.
Completion of Phase 1 Compensation and Resettlement Programme
Following resolution of the historical legal proceedings, Globe announced on 24
September 2026 that compensation payments had been completed for all 203
Project Affected Persons (PAPs) within the Phase 1 development area at Kanyika.
This milestone followed an extensive assessment and consultation process involving
the Government of Malawi, M'mbelwa District Council, the Ministry of Lands,
independent consultants, community representatives and affected households.
The process commenced with a community and stakeholder engagement forum on
27 April 2026, followed by a detailed census and asset survey between 1 and 12 May
2026. Government verification of household assets was subsequently undertaken
between 26 May and 1 June 2026.
The assessment included identification and valuation of land, structures, businesses,
crops, trees and other affected assets, with individual households provided the
opportunity to verify their compensation entitlements.
Following completion of the assessment and verification process, compensation
payments were made directly into individual PAP bank accounts between 21 and 23
September 2026.
The total Phase 1 compensation and resettlement budget is approximately MWK 3.09
billion (A$2.5 million), comprising approximately MWK 2.42 billion in direct PAP
compensation, MWK 59.2 million for community assets and additional funding for
livelihood restoration and transitional support.
The programme includes agricultural assistance, such as seeds and fertiliser, to
support affected households in re-establishing farming activities and livelihoods
following relocation.
Following receipt of compensation, households have a three-month period to relocate
and re-establish their homes and livelihoods. The Government of Malawi and local
Chiefs have confirmed that Globe may access and use compensated land during this
period while relocation continues.
The completion of Phase 1 compensation represents a significant land access
milestone, enabling Globe to progress initial mining and construction activities while
the broader resettlement programme continues in parallel.
Mining Licence and Regulatory Development Pathway
During September 2026, Globe continued its engagement with the MMRA regarding
the commencement of substantial on-site mine development at Kanyika.
Under the Mining Development Agreement (MDA) signed with the Government of
Malawi in March 2023, the Company was required to commence substantial mining
operations within the prescribed period. Following previous extensions, the
applicable deadline had been extended to 27 September 2026.
On 24 September 2026, Globe submitted a detailed report to the MMRA outlining the
physical development activities undertaken, the completion of community
compensation and resettlement milestones, and the progress made in preparing the
Project for mining and construction.
On 25 September 2026, the MMRA provided further guidance outlining the physical
development activities expected over the following six months to demonstrate
commencement of substantial on-site mine development.
The guidance identified the commencement of permanent mine infrastructure,
including the processing plant, tailings storage facility, site offices and run-of-mine
(ROM) pad, as applicable.
On 28 September 2026, Globe announced the regulatory pathway outlined by the
MMRA, which was subject to ratification by the MMRA Board.
Should the proposed six-month extension and associated development requirements
be ratified by the MMRA Board, the Company may need to secure significant
additional funding to undertake the prescribed works within the extension period.
The Company is progressing the engineering scope, sequencing and implementation
requirements for these works and intends to confirm the relevant measurable
development parameters with the MMRA and Government authorities before
committing material capital expenditure.
These activities are consistent with the infrastructure required to advance Kanyika
towards commercial production in early 2028.
Subsequent Event – Commencement of Early Mining Activities
On 23 October 2026, Globe announced the commencement of early mining activities
at the Kanyika Niobium and Tantalum Project, following completion of Phase 1
compensation payments, access road upgrades, site clearing and other preparatory
development works.
The mining programme involves the progressive development of strategically located
pits across the main Kanyika orebody, with excavation undertaken in successive
batches of approximately 5,000 tonnes. The programme is designed to extract
mineralised material for bulk sampling and grade verification, improve confidence in
existing Mineral Resource estimates and establish niobium-bearing ore stockpiles for
future processing plant commissioning and testing. Suitable non-ore-bearing material
is being utilised for processing plant terraces, foundations, roads and other
supporting infrastructure.
Image 2: The completed pit number 1
Initial mining observations indicate predominantly fine-grained, unconsolidated
material, with no significant hard rock encountered. Mining activities are being
undertaken by local contractor OG Plant Hire under Globe's on-site technical
supervision. The commencement of mining was also supported by local traditional
authorities, with three area chiefs attending a formal site handover ceremony.
Image 3: Traditional handover ceremony at Kanyika, marking the formal handover of the
site to contractors for the commencement of mining activities.
Quarterly Market Update
Niobium and Tantalum Market Update – Quarter Ended 30 September 2026
Niobium Market
During the September 2026 quarter, niobium prices remained relatively stable,
broadly in line with levels recorded during the corresponding period in 2025.
Global niobium production remains highly concentrated, with Brazilian producer
CBMM accounting for approximately 77% of global supply and three major
operations accounting for almost all primary production.
This concentration continues to highlight the strategic importance of developing
alternative sources of niobium outside the established producing regions.
Niobium demand continued to be supported by high-strength steel applications, while
aerospace, superalloys and advanced battery technologies represent additional
markets for high-purity niobium products.
Tantalum Market
Tantalum market conditions remained very strong during the September 2026
quarter, with concentrate prices sustained at multi-decade highs following an
increase of approximately another 43% (per Asia Metals) earlier in the quarter.
The increase was driven by supply disruptions in the Democratic Republic of Congo
(DRC) and Rwanda, together with continued demand from the capacitor and
electronics industries.
During September, market reports indicated continued firm pricing, with African and
Brazilian concentrate exporters increasing offers and Chinese tantalum pentoxide
suppliers quoting higher prices.
Supply-chain security and responsible sourcing remained important market
considerations, particularly given the concentration of tantalum production in Central
Africa and ongoing concerns regarding traceability of mineral exports.
Cash position
At the end of the September 2026 quarter, the Company had debt (included accrued
interest) of $2.26 (30 June 2026: $$Nil) and held cash of $3.52 million (30 June 2026:
$2.78 million).
ASX additional information
ASX Listing Rule 5.3.1: There were no substantive mining exploration activities during
the quarter. Work was confined to evaluation. The Company expended approximately
$2,589,000 on evaluation activities (refer section 2.1(d) of Appendix 5B).
ASX Listing Rule 5.3.2: There were no substantive mining production and
development activities during the quarter.
ASX Listing Rule 5.3.5: A total of $74,000 was paid to related parties during the
quarter comprising Non-Executive Directors’ fees (including superannuation).
Shareholding information
At 30 September 2026, shares on issue totalled 961,013,203.
The number and distribution of holders at 30 September 2026 was:
Holding Ranges Holders Holding % IC
above 0 up to and including 1,000 47 1,709 0.00%
above 1,000 up to and including 5,000 38 126,602 0.01%
above 5,000 up to and including 10,000 76 616,805 0.06%
above 10,000 up to and including 100,000 285 12,561,246 1.31%
above 100,000 134 947,706,841 98.62%
Totals 580 961,013,203 100.00%
Top 20 holders at 30 September 2026
Position Holder Name Holding % IC
1 APOLLO METALS INVESTMENT
COMPANY LIMITED
351,405,158 36.57%
2 AVOCADO TRADING LIMITED 136,500,000 14.20%
3 TRIPLE TALENT ENTERPRISES LTD 125,621,035 13.07%
4 AO-ZHONG INTERNATIONAL MINERALRE
SOURCES PTY LTD
118,143,062 12.29%
5 SUITABLE PIONEER LIMITED 33,500,000 3.49%
6 HONG KONG GREEN ENERGY
INDUSTRIAL CO LIMITED
23,103,975 2.40%
7 MS JENNIFER CHING PING 17,063,845 1.78%
8 BNP PARIBAS NOMINEES PTY LTD
<IB AU NOMS RETAILCLIENT>
15,459,695 1.61%
9 BNP PARIBAS NOMINEES PTY LTD
<CLEARSTREAM>
15,010,450 1.56%
10 CITICORP NOMINEES PTY LIMITED 14,030,223 1.46%
11 PATRAS CAPITAL PTE LTD 14,000,000 1.46%
12 MR COLIN ROBERT SEARL &
MRS CYNDA SEARL
12,349,888 1.29%
13 BNP PARIBAS NOMS PTY LTD 8,759,151 0.91%
14 C & CR SUPERCO PTY LTD
<C & CR SEARL SUPERFUND A/C>
6,306,295 0.66%
15 GOENG INVESTMENTS PTY LTD
<GOENG PENSION FUND A/C>
3,858,697 0.40%
16 BENRET PTY LTD
<COLIN SEARL FAMILY A/C>
3,671,263 0.38%
17 HSBC CUSTODY NOMINEES
(AUSTRALIA) LIMITED - A/C 2
3,039,844 0.32%
18 MR BAHRAM REZAEI 2,631,797 0.27%
19 GOTHA STREET CAPITAL PTY LTD
<BLUE SKY NO 2 A/C>
2,631,387 0.27%
20 MR KELLY PETER BODMAN 2,520,562 0.26%
Total 909,606,327 94.65%
Total issued capital 961,013,203 100.00%
Schedule of mineral tenements at 30 September 2026
Country Project Type Status Tenement Interest held by Globe Africa
30 September
2026
30 June 2026
Malawi Kanyika
Mining
Licence
Granted LML0216/21* 100% 100%
There were no tenements acquired or disposed of during the quarter.
* Pursuant to the Mines and Minerals Act, the Malawi Government is entitled to a 10%
free equity interest in LML0216/21 subject to formally notifying Globe Africa of its
desire to take up its entitlement. As at the date of this report, neither the Company
nor Globe Africa has received any such notice.
Authorisation for release
This report was authorised for release by the Board of Directors.
For further information, please contact:
Globe Metals & Mining Limited
Charles Altshuler
Interim Chief Executive Officer
P: +61 8 6118 7240
E: ca@globemm.com
About the Kanyika Niobium Project
The Kanyika Niobium Project is located in central Malawi, approximately 55km northeast of
the regional centre of Kasangu and is secured by Large-Scale Mining Licence No.
LML0216/21 which grants the Company security of tenure and the right to mine niobium,
tantalum, zirconium and other minor metals.
Drilling programs totalling 33.8 kilometres of percussion and core drilling have defined the
extent of mineralisation. Structured and progressive engineering studies have resulted in the
current (JORC 2012) Mineral Resource Estimate (refer below) and given rise to significant
improvements and simplifications in the process flowsheet.
The Kanyika Project will be developed in phases, substantially de-risking the project. The
project will be fully integrated on the mine site – Mining, Concentration and Refining, to
produce high-purity, high-value Niobium and Tantalum oxides for direct export to international
markets.
A Mineral Resource Estimate for the Kanyika Niobium Project under the 2012 JORC
guidelines was reported to ASX on 11 July 2018 as follows:
Mineral Resource Estimates
The information in this report that relates to Mineral Resources is extracted from the report titled
“Kanyika Niobium Project – Updated JORC Resource Estimate” released to the Australian Securities
Exchange (ASX) on 11 July 2018 and available to view at www.globemm.com and for which Competent
Persons’ consents were obtained. Each Competent Person’s consent remains in place for subsequent
releases by the Company of the same information in the same form and context, until the consent is
withdrawn or replaced by a subsequent report and accompanying consent.
The Company confirms that is not aware of any new information or data that materially affects the
information included in the original ASX announcement released on 11 July 2018 and, in the case of
estimates of Mineral Resources, that all material assumptions and technical parameters underpinning
the estimates in the original ASX announcement continue to apply and have not materially changed. The
Company confirms that the form and context in which the Competent Persons’ findings are presented
have not been materially modified from the original ASX announcement.
Full details are contained in the ASX announcement released on 11 July 2018 titled “Kanyika Niobium
Project – Updated JORC Resource Estimate” available to view at www.globemm.com.
Table 1: MRE for KNP using a 1,500 ppm Nb2O5 lower cut Table 2: MRE for KNP using a 3,000 ppm Nb2O5 lower cut
Category
Resource
(Mt)
Nb2O5 (ppm) Ta2O5 (ppm) Category
Resource
(Mt)
Nb2O5 (ppm) Ta2O5 (ppm)
Measured 5.3 3,790 180 Measured 3.4 4,790 220
Indicated 47 2,860 135 Indicated 16.6 4,120 160
Inferred 16 2,430 120 Inferred 2.8 4,110 190
TOTAL 68.3 2,830 135 TOTAL 22.8 4,220 190
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
GLOBE METALS & MINING LIMITED
ABN Quarter ended (“current quarter”)
33 114 400 609 30 September 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months) $A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (247) (247)
(e) administration and corporate costs (194) (194)
1.3 Dividends received (see note 3) - -
1.4 Interest received 8 8
1.5 Interest and other costs of finance paid (39) (39)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material)
(a) Exploration and evaluation
payments for assets disposed
(b) Insurance recoveries
-
-
-
-
-
-
1.9 Net cash from / (used in) operating
activities
(472) (472)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (12) (12)
(d) exploration & evaluation (2,589) (2,589)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months) $A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other - funds from joint ventures - -
2.6 Net cash from / (used in) investing
activities
(2,601) (2,601)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options 1,594 1,594
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(11) (11)
3.5 Proceeds from borrowings 2,229 2,229
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other – operating lease payments - -
3.10 Net cash from / (used in) financing
activities
3,812 3,812
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
2,779 2,779
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(472) (472)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(2,601) (2,601)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
3,812 3,812
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months) $A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
3,518 3,518
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances (includes cash from assets
held for sale)
3,518 1,366
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (term deposits) - 1,413
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
3,518 2,779
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
74
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Payments relate to Director’s fees and their associates
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cas