Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
Globe Metals & Mining Limited
ABN 33 114 400 609
45 Ventnor Avenue
West Perth WA 6005
ASX: GBE
+61 8 6118 7240
info@globemm.com
globemm.com
ASX Announcement
31 October 2025
Quarterly Activities Report – September 2025 Quarter
Solid operational, regulatory, and financial progress, positioning Globe
for the next phase of development at Kanyika.
Highlights
• The Malawi Mines and Minerals Regulatory Authority (MMRA) confirmed a 12-
month extension under the Mining Development Agreement (MDA), allowing
Kanyika Niobium Project (Project) to commence substantial mining operations by
27 September 2026.
• Globe’s Large-Scale Mining Licence LML0216/21 was formally amended to
include zircon, hafnium, neodymium, and praseodymium, broadening the
Project’s exposure to high-growth critical mineral markets.
• Dr Joseph Mkandawire, the former Principal Secretary of Malawi’s Ministry of
Mining, has joined the board of Globe Metals & Mining Africa Ltd., strengthening
local leadership and regulatory alignment.
• Post-quarter end, Tranche 1 of the A$8.67 million private placement (Placement)
raised A$6.96 million, coupled with the full conversion of Ms Jennifer Ping’s
US$540,000 loan to equity, with ongoing discussions for a partial loan-to-equity
conversion with Mr Bo Tan.
• The U.S. Geological Survey (USGS) ranked niobium #10 on its Draft 2025 Critical
Minerals List, highlighting a potential US$10.4 billion GDP loss for the U.S. under
a full-supply-disruption scenario, underscoring Kanyika’s global strategic
importance.
▪ Cash at bank at the end of the September 2025 quarter was $0.31 million (30
June 2025: $0.50 million).
Globe Metals & Mining Limited (ASX: GBE) (Globe or Company) is pleased to
announce its Appendix 5B cashflow report for the quarter ended 30 September 2025
(Q1 FY26), together with the following operational update.
This quarter marked a significant advancement in de-risking and progressing the
Kanyika Niobium Project, strengthening Globe’s capital base, regulatory position, and
strategic importance in the global critical minerals supply chain.
Globe’s Interim Chief Executive Officer, Charles Altshuler, commented:
“During this quarter, we demonstrated continuous progress across Globe’s
operational, regulatory, and funding fronts. The MDA extension provides the certainty
needed to complete key infrastructure and resettlement milestones, while the
expansion of our mining licence underscores Kanyika’s increasing relevance in the
global critical minerals landscape.
The successful completion of Tranche 1 and the loan conversions after the quarter
have materially strengthened our balance sheet and demonstrated continued support
from our strategic investors. We are now poised to enter the next development phase
with a cleaner capital structure, a broader resource base, and stronger relationships
with government, community, and funding partners.
The recognition of niobium as a top-ten strategic mineral by U.S. Geological Survey,
with an associated potential economic impact of US$10 billion under supply chain
disruptions, highlights both the importance and the opportunity inherent in the
Kanyika project. Globe remains committed to advancing the Project responsibly,
efficiently, aligning closely with Malawi’s national development priorities.”
Project and Permitting Update
During the quarter, the Company received confirmation from MMRA that the MDA for
the Kanyika Niobium Project remains valid and in full effect. The MMRA granted a 12-
month extension for the commencement of substantial mining operations by 27
September 2026.
This extension follows collaborative efforts with the Government of Malawi to
synchronize key development activities with national infrastructure delivery
schedules. Over the past year, Globe has advanced various preparatory milestones,
including early contractor engagement, infrastructure planning, and formalisation of
the Community Development Agreement (CDA), which establishes the Kanyika
Development Trust for local benefit sharing.
The extension period will enable the Company to finalise critical activities with the
government agencies, including completion of the 32-km access road from
Chatoloma Junction to site, advancing the 17-MW grid power connection, and
implementing the resettlement and compensation program for affected households.
Globe is working closely with the District Commissioner and community leaders to
synchronize these processes with pre-construction and early works.
In the next 12 months, Globe’s focus will shift to resettlement preparations, site-
based assessments, and advancing early works and permitting activities vital for full
construction readiness. The Company continues to work transparently with
regulators, communities, and investors to ensure that the Project progresses toward
substantial mining operations in a responsible and ESG-aligned manner.
Licence Expansion and Critical Minerals Diversification
During the quarter, Globe received formal approval from the MMRA for an
amendment to Large-Scale Mining Licence (LML0216/21) for the Kanyika Niobium
Project. The amendment extends the licence scope beyond niobium, tantalum, and
uranium to include zircon, hafnium, neodymium, and praseodymium — four high-
value critical minerals with strong strategic relevance to global clean energy and
advanced materials markets.
This regulatory approval enhances the long-term development potential of the
Project and ensures all future production of these minerals will occur under a fully
compliant, government-endorsed framework. It also aligns the Project with the
broader priorities of Malawi’s Vision 2063, which seeks to establish the country as a
regional hub for critical mineral production and processing.
Each of the newly included minerals offers unique commercial and strategic
advantages:
• Zircon: Used in ceramics and advanced refractories, it can be recovered as a
by-product of niobium and tantalum processing, bringing additional revenue
with minimal capital investment.
• Hafnium: A rare and ultra-high-value metal used in aerospace superalloys
and nuclear control rods, representing a potential long-term opportunity for
Globe as global demand outpaces supply.
• Neodymium and praseodymium : Essential for high-performance permanent
magnets used in EVs and wind turbines, reinforcing the Project’s exposure to
the fast-growing green-energy and electrification sectors.
Community, ESG and Leadership
During the quarter, Globe strengthened its in-country leadership with the
appointment of Dr. Joseph Mkandawire to the Board of its Malawian subsidiary,
Globe Metals & Mining Africa Limited. Dr. Mkandawire is the former Principal
Secretary of Malawi’s Ministry of Mining, his extensive experience in government and
policy will support the Company’s community, regulatory, and national development
alignment.
Strategic Update and BFS Progress
During the quarter, the Company continued the engineering optimisation, Early
Contractor Involvement (ECI) engagement, and funding strategy workstreams
outlined in the June quarter report. These activities advanced as planned, with further
refinement of project scope, cost estimates, and partner engagement.
Having already detailed the ECI model and associated design improvements in the
previous update, the Company’s focus this quarter has been on updating contractor
input, integrating updated market data into the BFS, and progressing partner due
diligence ahead of the Final Investment Decision (FID).
These ongoing efforts maintain Globe’s strong strategic position and ensure that the
Kanyika Niobium Project remains aligned with market demand, ESG expectations,
and financing readiness.
The Company will release the BFS at a strategically aligned time following these
partnership and procurement negotiations. While no binding EPC or construction
contracts are yet in place, this early engagement is expected to significantly de-risk
the project execution phase.
Post-Quarter-End Funding and Capital Structure Update
Following the end of the September 2025 quarter, Globe successfully completed
several key financing initiatives that further strengthened its balance sheet and
advanced the Kanyika Niobium Project toward development readiness.
In early October 2025, the Company completed Tranche 1 of its A$8.67 million two-
tranche private placement (Placement), raising A$6.96 million through the issue of
136.5 million shares at A$0.051 per share to Avocado Trading Limited, a Hong Kong–
based institutional investor. The Placement was completed under Globe’s existing
ASX Listing Rule 7.1/7.1A capacity, with proceeds allocated to project pre-
development, debt reduction, and general working capital.
Subsequently, Ms Jennifer Ping, an existing lender, converted her entire US$540,000
loan (plus accrued interest) into equity at A$0.051 per share. This conversion fully
extinguishes her debt and underscores continued confidence in Globe’s growth
strategy and execution pathway.
In parallel, discussions continue with Director and major shareholder Mr Bo Tan
regarding the partial conversion of his A$2.3 million shareholder loan into equity on
the same terms as the Placement, and are also subject to AGM approval. The
repayment dates for both the A$2.3 million and US$1.4 million facilities as shown in
the tables below have been extended to 30 November 2025, with a further extension
to 31 May 2026 for the A$2.3 million facility to allow sufficient time to finalise the
conversion arrangements.
Globe is also finalising arrangements for Tranche 2 of the Placement, which
comprises 33.5 million shares and 190 million free-attaching options (exercisable at
A$0.069). Settlement of Tranche 2 is scheduled to occur immediately following
shareholder approval at the Annual General Meeting on 27 November 2025, with
funds to be applied to advance early-works programs, offtake marketing, and
permitting activities ahead of Final Investment Decision (FID).
Collectively, these transactions are expected to materially reduce Globe’s debt
exposure, enhance its capital structure, and provide greater financial flexibility as the
Company advances the Kanyika Niobium Project toward financing and early
construction.
Global Market Context and Niobium Supply Dynamics
In August 2025, the USGS released its Draft 2025 Critical Minerals List and
accompanying analysis of economic exposure to mineral-supply disruptions. The
study, published on 26 August 2025, evaluated 84 mineral commodities across more
than 1,200 trade-disruption scenarios, covering the potential effects on over 400 U.S.
industries. Within this comprehensive assessment, niobium ranked 10th overall in the
probability-weighted index of potential U.S. GDP loss — placing it firmly among the
most strategically important critical minerals. The USGS model indicated that a
complete disruption of U.S. niobium imports (predominantly sourced from Brazil,
which controls over 85% of global production) would result in a gross GDP loss of
approximately US$10.4 billion, with a probability-weighted impact of around US$394
million under the most likely scenario.
The report highlighted that niobium’s elevated ranking stems from its severe supply
concentration, coupled with its essential role in aerospace superalloys, high-strength
steels, electronics, medical devices, and advanced infrastructure materials. The
USGS further noted that supply vulnerabilities are magnified by geopolitical exposure
to single-country production and export controls, which could significantly disrupt
downstream U.S. manufacturing sectors. The draft 2025 list and underlying
methodology will guide future federal policy, including permitting, tax incentives, and
domestic processing initiatives under the Department of the Interior’s critical minerals
strategy. Niobium’s inclusion in the top-ten ranking has, therefore, drawn heightened
attention from investors and policymakers, reinforcing its status as a strategic
material of national importance and strengthening the case for diversified supply
sources, including projects such as Globe’s Kanyika Niobium Project in Malawi.
Cash position
At the end of the September 2025 quarter, the Company had debt (included accrued
interest) of $5.7 million (30 June 2025: $4.5 million) and held cash of $0.31 million
(30 June 2025: $0.50 million).
Convertible Note – Ms Jennifer Ping
During the quarter, Globe drew down US$170,000 (A$260,000) under its A$520,000
convertible note facility with Ms Jennifer Ping to fund working capital requirements.
The note carries a 20% annual coupon, is unsecured, and convertible (in whole or in
part) into fully paid ordinary shares at a 20% discount to the 15-day VWAP. At the
end of the quarter the company had undrawn US$170,000 (A$260,000) on this
facility.
On 28 July 2025, the Company announced that it had raised A$520,000 via a
convertible note issue to support short-term working capital requirements. The Note
was issued to Ms Jennifer Ping, an overseas investor who is not a related party of the
Company.
The key terms of the Convertible Note with Ms Jennnifer Ping are as follows:
Facility limit: A$520,000 (US$340,000)
Drawdowns: Two equal drawdowns of A$260,000 each on 1 September
2025 and 1 October 2025
Term: 6 months from issue (28 July 2025)
Interest rate: 20% per annum, payable in cash on maturity or upon
conversion, at the noteholder’s election
Conversion: Convertible (in whole or in part) at any time during or on expiry
of the 6-month term at a 20% discount to the 15-day VWAP
immediately prior to conversion
Adjustment for
placement:
If the Company conducts a placement during the term, the
conversion price will be the lower of (i) the placement price; or
(ii) the price determined using the 20% discount to the 15-day
VWAP.
Early repayment: The Company may, at its discretion, repay all or part of the face
value and accrued interest at any time prior to maturity, subject
to a 5% early repayment premium.
Security: Unsecured
Repayment: Unless converted or repaid earlier, the face value and all
accrued interest are payable in full on the maturity date.
Loan Facility – Mr Bo Tan
During the quarter, the Company also completed the final drawdown of US$200,000
(A$303,176) under its US$1.4 million unsecured loan facility with Director Mr Bo Tan.
The facility bears interest at 20% per annum and matures on 18 October 2025.
At 30 June 2025, A$4.5 million had been drawn down under its loan facilities with Mr
Tan, with an amount of A$300,000 still available for drawdown.
The key terms of the first loan facility with Mr Tan Bo are as follows:
Facility limit: A$2,300,000
Drawdowns: Monthly drawdowns as follows:
o A$500,000 by no later than 25 September 2024);
o A$500,000 no earlier than 1 October 2024;
o A$500,000 no earlier than 1 November 2024; and
o A$800,000 no earlier than 1 December 2024.
Interest rate: 25% per annum accruing and payable daily, with interest to be
capitalised daily and added to the aggregate principal amount
outstanding, as adjusted for any capitalised interest,
prepayments, or repayments (Principal Outstanding). Interest
is payable on overdue amounts that are unpaid at the rate of
0.5% per day.
Term: 25 August 2025, has been further extended to 31 May 2026
Early repayment: The Company may prepay all or part of the Principal
Outstanding at any time prior to the due date for repayment
provided that if Globe prepays all of the Principal Outstanding
prior to the repayment date it must pay to the lender an amount
equivalent to one calendar month’s interest on the Principal
Outstanding at the same time as it prepays the Principal
Outstanding.
Security: The loan facility is unsecured.
The key terms of the additional loan facility with Mr Tan Bo are as follows:
Facility limit: Up to US$1.4 million denominated in US$
Early
cancellation:
The first US$400,000 is guaranteed for drawdown, and
thereafter, the lender may cancel the remaining tranches under
the loan facility if Globe secures alternative funding for an
amount not less than the undrawn tranches at that time.
Drawdowns: - On 15 February 2025: US$200,000
- On 1 March 2025: US$200,000
- On 15 March 2025: US$200,000
- On 1 April 2025: US$300,000
- On 15 April 2025: US$300,000
- On 1 June 2025: US$200,000
Interest rate: 20% per annum accruing and payable daily, with interest to be
capitalised daily and added to the aggregate principal amount
outstanding, as adjusted for any capitalised interest,
prepayments, or repayments (Principal Outstanding). Interest
is payable on overdue amounts that are unpaid at the rate of
0.5% per day.
Term: 18 October 2025, has been extended to 30 November 2025
Early repayment: The Company may prepay all or part of the Principal
Outstanding at any time prior to the due date for repayment,
provided that if Globe prepays all of the Principal Outstanding
prior to the repayment date it must pay to the lender an amount
equivalent to one calendar month’s interest on the Principal
Outstanding at the same time as it prepays the Principal
Outstanding.
Security: The loan facility is unsecured.
ASX additional information
ASX Listing Rule 5.3.1: There were no substantive mining exploration activities during
the quarter. Work was confined to evaluation. The Company expended approximately
$153,000 on evaluation activities (refer section 2.1(d) of Appendix 5B).
ASX Listing Rule 5.3.2: There were no substantive mining production and
development activities during the quarter.
ASX Listing Rule 5.3.5: A total of $91,000 was paid to related parties during the
quarter comprising Non-Executive Directors’ fees (including superannuation).
Globe Metals & Mining Limited
ABN 33 114 400 609
45 Ventnor Avenue
West Perth WA 6005
ASX: GBE
+61 8 6118 7240
info@globemm.com
globemm.com
Shareholding information
At 30 September 2025, shares on issue totalled 694,653,010.
The number and distribution of holders at 30 September 2025 was:
Holding Ranges Holders Holding % IC
above 0 up to and including 1,000 46 2,514 0.00%
above 1,000 up to and including 5,000 38 121,151 0.02%
above 5,000 up to and including 10,000 58 471,758 0.07%
above 10,000 up to and including
100,000 277 12,234,600 1.76%
above 100,000 135 681,822,987 98.15%
Totals 554 694,653,010 100.00%
Top 20 holders at 30 September 2025
Position Holder Name Holding % IC
1 APOLLO METALS INVESTMENT
COMPANY LIMITED
351,405,158 50.59%
2 AO-ZHONG INTERNATIONAL MINERALRE
SOURCES PTY LTD
118,143,062 17.01%
3 TRIPLE TALENT ENTERPRISES LTD 69,428,662 9.99%
4 BNP PARIBAS NOMINEES PTY LTD
<CLEARSTREAM>
17,992,515 2.59%
5 PATRAS CAPITAL PTE LTD 14,000,000 2.02%
6 MR COLIN ROBERT SEARL &
MRS CYNDA SEARL
12,349,888 1.78%
7 CITICORP NOMINEES PTY LIMITED 11,966,884 1.72%
8 BNP PARIBAS NOMINEES PTY LTD
<IB AU NOMS RETAILCLIENT>
8,669,231 1.25%
9 BNP PARIBAS NOMS PTY LTD 6,023,863 0.87%
10 BENRET PTY LTD
<COLIN SEARL FAMILY A/C>
5,373,888 0.77%
11 C & CR SUPERCO PTY LTD
<C & CR SEARL SUPERFUND A/C>
4,168,888 0.60%
12 MR RICHARD ULRICK &
MRS WENDY ULRICK
<ULRICK SUPER FUND A/C>
3,934,439 0.57%
13 GOENG INVESTMENTS PTY LTD
<GOENG PENSION FUND A/C>
3,858,697 0.56%
14 HSBC CUSTODY NOMINEES
(AUSTRALIA) LIMITED - A/C 2
3,039,844 0.44%
15 GOTHA STREET CAPITAL PTY LTD
<BLUE SKY NO 2 A/C>
2,870,100 0.41%
16 M & K KORKIDAS PTY LTD
<M & K KORKIDAS PTY LTD A/C>
2,765,100 0.40%
17 MR KELLY PETER BODMAN 2,520,562 0.36%
18 MR BAHRAM REZAEI 2,500,000 0.36%
19 MR DRITAN MEHMETI 2,000,000 0.29%
20 MR MARK LEONARD SWANSON 1,725,000 0.25%
Total 644,735,781 92.81%
Total issued capital - ordinary 694,653,010 100.00%
Schedule of mineral tenements at 30 September 2025
Country Project Type Status Tenement Interest held by Globe Africa
30 September
2025
30 June 2025
Malawi Kanyika
Mining
Licence
Granted LML0216/21* 100% 100%
There were no tenements acquired or disposed of during the quarter.
* Pursuant to the Mines and Minerals Act, the Malawi Government is entitled to a 10%
free equity interest in LML0216/21 subject to formally notifying Globe Africa of its
desire to take up its entitlement. As at the date of this report, neither the Company
nor Globe Africa has received any such notice.
Authorisation for release
This report was authorised for release by the Board of Directors.
For further information, please contact:
Globe Metals & Mining Limited
Charles Altshuler
Interim Chief Executive Officer
P: +61 8 6118 7240
E: ca@globemm.com
About the Kanyika Niobium Project
The Kanyika Niobium Project is located in central Malawi, approximately 55km northeast of
the regional centre of Kasangu and is secured by Large-Scale Mining Licence No.
LML0216/21 which grants the Company security of tenure and the right to mine niobium,
tantalum, zirconium and other minor metals.
Drilling programs totalling 33.8 kilometres of percussion and core drilling have defined the
extent of mineralisation. Structured and progressive engineering studies have resulted in the
current (JORC 2012) Mineral Resource Estimate (refer below) and given rise to significant
improvements and simplifications in the process flowsheet.
The Kanyika Project will be developed in phases, substantially de-risking the project. The
project will be fully integrated on the mine site – Mining, Concentration and Refining, to
produce high-purity, high-value Niobium and Tantalum oxides for direct export to international
markets.
A Mineral Resource Estimate for the Kanyika Niobium Project under the 2012 JORC
guidelines was reported to ASX on 11 July 2018 as follows:
Mineral Resource Estimates
The information in this report that relates to Mineral Resources is extracted from the report titled
“Kanyika Niobium Project – Updated JORC Resource Estimate” released to the Australian Securities
Exchange (ASX) on 11 July 2018 and available to view at www.globemm.com and for which Competent
Persons’ consents were obtained. Each Competent Person’s consent remains in place for subsequent
releases by the Company of the same information in the same form and context, until the consent is
withdrawn or replaced by a subsequent report and accompanying consent.
The Company confirms that is not aware of any new information or data that materially affects the
information included in the original ASX announcement released on 11 July 2018 and, in the case of
estimates of Mineral Resources, that all material assumptions and technical parameters underpinning
the estimates in the original ASX announcement continue to apply and have not materially changed. The
Company confirms that the form and context in which the Competent Persons’ findings are presented
have not been materially modified from the original ASX announcement.
Full details are contained in the ASX announcement released on 11 July 2018 titled “Kanyika Niobium
Project – Updated JORC Resource Estimate” available to view at www.globemm.com.
Table 1: MRE for KNP using a 1,500 ppm Nb2O5 lower cut Table 2: MRE for KNP using a 3,000 ppm Nb2O5 lower cut
Category
Resource
(Mt)
Nb2O5 (ppm) Ta2O5 (ppm) Category
Resource
(Mt)
Nb2O5 (ppm) Ta2O5 (ppm)
Measured 5.3 3,790 180 Measured 3.4 4,790 220
Indicated 47 2,860 135 Indicated 16.6 4,120 160
Inferred 16 2,430 120 Inferred 2.8 4,110 190
TOTAL 68.3 2,830 135 TOTAL 22.8 4,220 190
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
GLOBE METALS & MINING LIMITED
ABN Quarter ended (“current quarter”)
33 114 400 609 30 September 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (232) (232)
(e) administration and corporate costs (355) (355)
1.3 Dividends received (see note 3) - -
1.4 Interest received - -
1.5 Interest and other costs of finance paid (1) (1)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material)
(a) Exploration and evaluation
payments for assets disposed
(b) Insurance recoveries
-
-
-
-
-
-
1.9 Net cash from / (used in) operating
activities
(588) (588)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) exploration & evaluation (153) (153)
(e) investments - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
(f) other non-current assets - -
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other - funds from joint ventures - -
2.6 Net cash from / (used in) investing
activities
(153) (153)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
- -
3.5 Proceeds from borrowings 563 563
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other – operating lease payments - -
3.10 Net cash from / (used in) financing
activities
563 563
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
496 496
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(588) (588)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(153) (153)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
563 563
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
318 318
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances (includes cash from assets
held for sale)
318 496
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (term deposits) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
318 496
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
91
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Payments relate to Director’s fees and their associates
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at quarter
end
$A’000
7.1 Loan facilities 5,313 5,053
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities 5,313 5,053
7.5 Unused financing facilities available at quarter end 260
7.6 Include in the box below a description of each facility above, including the lender, interest rate, maturity
date and whether it is secured or unsecured. If any additional financing facilities have been entered into
or are proposed to be entered into after quarter end, include a note providing details of those facilities as
well.
Convertible Note Facilities
On 29 July 2025, the Company issued a A$520,000 unsecured convertible note to an overseas investor.
The note has a six-month term to 29 January 2026 and bears interest at 20% per annum, payable on
maturity.
On 1 May 2025, the Company issued a A$300,000 unsecured convertible note to an overseas investor.
The note has a six-month term and bears interest at 20% per annum, payable on maturity.
Further details of the terms and conditions of these notes are set out in the Company’s Annual Report.
Loan Facilities
On 30 January 2025, the Company entered into an unsecured short-term loan facility with Director Bo Tan
for US$1,400,000. The repayment date is 30 November 2025. Interest is payable at 20% per annum.
In September 2024, the Company entered into an unsecured short-term loan facility with Director Bo Tan
for A$2,300,000. The repayment date is 30 November 2025. Interest is payable at 25% per annum.
Subsequent to quarter end, the Company announced a proposed A$8.67 million placement to provide
funding for ongoing exploration and working capital.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (588)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(153)
8.
Share your feedback
Discover