ASX Announcement
7 June 2024
Chlorination refinery pilot plant installed and hot
commissioned
Globe Metals & Mining Limited (ASX: GBE) (“Globe” or “Company”) is pleased to announce that the
chlorination refinery pilot plant for the production of niobium and tantalum product samples has now
been installed and hot commissioned 1.
The chlorination technology has a low environmental impact and low carbon footprint, which is
important to Globe’s operating philosophy. The plant was designed to produce very high purity –
99.98% – (optical grade) niobium pentoxide samples which will be provided to Globe’s key off-takes for
their technical assessment. Once the oxide product is produced, Globe will finalise its discussions with
key industry off-takers, representing a major step forward in the development of the Kanyika Project.
Hot Commissioning
Both the extraction plant (A) and distillation plant (B) have been installed and hot commissioned. A
process of optimisation of the refining process is now underway to start processing the Kanyika
concentrate to final product.
(A)
Extraction Pilot Plant
The extraction pilot plant consists of:
•
graphite reactor;
•
graphite transfer and cooling tube;
•
zircon and iron de-sublimer;
•
niobium and tantalum condenser; and
•
water scrubber for silica, titanium, etc.
The reactor processes 1kg/day of concentrate by heating carbon/concentrate pellets with chlorine gas.
Metal chlorides evaporate and condense at different temperatures. Niobium and tantalum chlorides
are captured together and transferred to the distillation column.
1 Globe’s ASX Announcement titled ‘Further metallurgical results on chlorination test work – correction’ made on
20 March 2024 contains the information required by ASX Listing Rule 5.16 regarding the stated production target.
All material assumptions underpinning the production target as announced on that date continue to apply and
have not materially changed.
Image 1: Pilot extraction set up: graphite reactor and transfer tube
(B)
Niobium/Tantalum Distillation Purification Plant
Purification of the tantalum/niobium chloride mixture is done via distillation. Heated above 250°C,
TaCl5, with a lower boiling point, concentrates as it ascends. Condensed at 230°C, TaCl5 is collected.
Once TaCl5 is removed, the remaining condensate, now pure NbCl5, is extracted.
Image 2: First run chloride products
2
Image 3: Two-stage, 2” distillation column
with thermal oil cooled condenser
Image 4: Operational distillation column after
commissioning
Paul Smith, Globe’s CEO commented: “We are incredibly pleased with the progress in metallurgical test
work. The production of high-quality niobium concentrate for the refinery pilot plant is advancing well.
Recovering high-quality niobium and tantalum oxides is crucial for finalising offtake agreements and the
updated feasibility study. We eagerly anticipate the results of the chlorination extraction test work and
the pilot plant's development and operation, which will be reported on shortly.”
Overview of the Carbochlorination Process
Chlorination metallurgy is a process for recovering and utilising ore resources by reacting metals, metal
oxides, sulphides, and other compounds with chlorine under specific conditions using chlorinating
agents (Cl2, NaCl, CaCl2, etc), forming metal chlorides (Minerals Engineering, Vol 154, 1 August 2020).
This method is well-established for recovering high-purity metals:
3
•
Zirconium: ATI Materials in the US pioneered this in the 1950s for zirconium chloride (ZrCl4)
and zirconium metal production, with other producers like CNNC Jinghuan, Westinghouse
Electric USA, and Framatome 1.
•
Silicon: Siemens and Wacker developed hyper-pure polysilicon production via chlorination in
the 1950s.
•
Niobium and Tantalum: Solikamsk Magnesium Works in Russia extract these from loparite ore.
•
Titanium: Tronox processes titanium ore and manufactures high-purity titanium chemicals.
The carbochlorination process involves:
1.
Mixing and pelletizing mineral concentrate with carbon powder.
2.
Reacting the pellets with chlorine to convert metal oxides to metal chlorides.
3.
Purifying niobium and tantalum chlorides using distillation.
4.
Oxidizing niobium and tantalum chlorides to oxides.
Next Steps
•
Niobium/tantalum will be extracted and separated using environmentally sustainable
chlorination refining.
•
Product samples will be provided to key off-takers as part of the offtake agreement finalisation
process.
•
The update of the Project Feasibility Study, inclusive of the in-country chlorination refinery.
•
The decision to execute and develop Phase 1 of the Project.
Technical Partners
As previously announced2, Globe is very proud to be working very closely with its key technical service
providers in the development of its concentrator and refinery development journey. These refinery
partners are TCM Research Ltd and the Resonant Group https://www.resonant.co.za/.
Authorisation for Release
This announcement has been authorised for release by the Company’s Chief Executive Officer, Paul
Smith.
2 Refer to ASX Announcement titled ‘Quarterly Activities/Appendix 5B Cash Flow Report’ made on 31 July 2023
4
For further information, please contact:
Paul Smith
Chief Executive Officer
+61 8 6118 7240
paul.smith@globemm.com
About the Kanyika Niobium Project
The Kanyika Niobium Project is located in central Malawi, approximately 55km northeast of the regional centre of
Kasangu and is secured by Large-Scale Mining Licence No. LML0216/21 which grants the Company security of
tenure and the right to mine niobium, tantalum, and deleterious uranium.
Drilling programs totalling 33.8 kilometres of percussion and core drilling have defined the extent of
mineralisation. Structured and progressive engineering studies have resulted in the current (JORC 2012) Mineral
Resource Estimate (refer below) and given rise to significant improvements and simplifications in the process
flowsheet.
The Kanyika operations will produce a pyrochlore mineral concentrate that contains both niobium and tantalum in
commercially valuable volumes to be shipped to a refinery for advanced processing into high purity materials.
A Mineral Resource Estimate for the Kanyika Niobium Project under the 2012 JORC guidelines was reported to
ASX on 11 July 2018 as follows:
5
Table 1: MRE for KNP using a 1,500 ppm Nb2 O5 lower cut
Category
Resource
(Mt)
Measured
5.3
Indicated
47
Nb2 O5 (ppm)
Table 2: MRE for KNP using a 3,000 ppm Nb2 O5 lower cut
Resource
(Mt)
Nb2 O5 (ppm)
Ta2 O5 (ppm)
Ta2 O5 (ppm)
Category
3,790
180
Measured
3.4
4,790
220
2,860
135
Indicated
16.6
4,120
160
Inferred
16
2,430
120
Inferred
2.8
4,110
190
TOTAL
68.3
2,830
135
TOTAL
22.8
4,220
190
Mineral Resource Estimates
The information in this report that relates to Mineral Resources is extracted from the report titled “Kanyika Niobium Project –
Updated JORC Resource Estimate” released to the Australian Securities Exchange (ASX) on 11 July 2018 and available to view
at www.globemm.com and for which Competent Persons’ consents were obtained. Each Competent Person’s consent remains
in place for subsequent releases by the Company of the same information in the same form and context, until the consent is
withdrawn or replaced by a subsequent report and accompanying consent.
The Company confirms it is not aware of any new information or data that materially affects the information included in the
original ASX announcement released on 11 July 2018 and, in the case of estimates of Mineral Resources, that all material
assumptions and technical parameters underpinning the estimates in the original ASX announcement continue to apply and
have not materially changed. The Company confirms that the form and context in which the Competent Persons’ findings are
presented have not been materially modified from the original ASX announcement.
Full details are contained in the ASX announcement released on 11 July 2018 titled ‘Kanyika Niobium Project – Updated JORC
Resource Estimate’ available to view at www.globemm.com.
6
Share your feedback
Discover